Project summary

SectorPulp & paperCompanyAndritz & Rigesa WestRock
LocationTrês Barras – SCApproximate investmentUS$ 50 million
Project no.OS 020Scope
  • Detailed design
  • Technical assistance on site

The main challenge

Detailed engineering for an OCC unit: atmospheric filters on a steel structure, a layout adjusted so rejects drain at the required slopes, instruments installed under operating conditions, and large purchased items fitted into tight space limits.

Key success indicators

Detailed engineering
Technical assistance during construction
Technical documentation of the works

Engecell's challenges

Designing in a small area
Being the first OCC reference unit
Eliminating vibration in pulsating and straight lines